English Dutch French German Portuguese Spanish
Menu

Onshore Environmental Risks - Terrestrial impacts and project footprint

Project footprints resulting from exploration and construction activities may include seismic tracks, well pads, temporary facilities, such as workforce base camps, material (pipe) storage yards, workshops, access roads, airstrips and helipads, equipment staging areas, and construction material extraction sites (including borrow pits and quarries).

Operational footprints may include well pads, permanent processing treatment, transmission and storage facilities, pipeline right-of-way corridors, access roads, ancillary facilities, communication facilities (e.g., antennas), power generation and transmission lines.

Impacts may include loss of or damage to, terrestrial habitat, creation of barriers to wildlife movement, soil erosion, and disturbance to water bodies including possible sedimentation, the establishment of non-native invasive plant species and visual disturbance. The extent of the disturbance will depend on the activity along with the location and characteristics of the existing vegetation, topographic features and waterways.

The visual impact of permanent facilities should be considered in design so that impacts on the existing landscape are minimized. The design should take advantage of the existing topography and vegetation, and should use low profile facilities and storage tanks if technically feasible and if the overall facility footprint is not significantly increased. In addition, consider suitable paint color for large structures that can blend with the background.

Additional prevention and control measures to minimize the footprint of onshore oil and gas developments may include the following:

  1. Establish all facilities in locations that avoid critical terrestrial and aquatic habitat and plan construction activities to avoid sensitive times of the year;
  2. Minimize land requirements for aboveground permanent facilities;
  3. Minimize areas to be cleared. Use hand cutting where possible, avoiding the use of heavy equipment such as bulldozers, especially on steep slopes, water and wetland crossings, and forested and ecologically sensitive areas;
  4. Use a central processing / treatment facility for operations, when practical;
  5. Minimize well pad size for drilling activities and satellite / cluster, directional, extended reach drilling techniques should be considered, and their use maximized in sensitive locations;
  6. Avoid construction of facilities in a floodplain, whenever practical, and within a distance of 100 m of the normal high-water mark of a water body or a water well used for drinking or domestic purposes;
  7. Consider the use of existing utility and transport corridors for access roads and pipeline corridors to the extent possible;
  8. Consider the routing of access roads to avoid induced impacts such as increased access for poaching;
  9. Minimize the width of a pipeline ROW or access road during construction and operations as far as possible;
  10. Limit the amount of pipeline trench left open during construction at any one time.
  11. Safety fences and other methods to prevent people or animals from falling into open trenches should be constructed in sensitive locations and within 500 m of human populations. In remote areas, install wildlife escape ramps from open trenches (typically every 1km where wildlife is present);
  12. Consider use of animal crossing structures such as bridges, culverts, and over crossings, along pipeline and access road rights-of-way;
  13. Bury pipelines along the entire length to a minimum of 1 m to the top-of-pipe, wherever this is possible;
  14. Carefully consider all of the feasible options for the construction of pipeline river crossings including horizontal directional drilling;
  15. Clean-up and fully reinstate following construction activities (including appropriate revegetation using native plant species following construction activities) the pipeline right-of-way and temporary sites such as workforce accommodation camps, storage yards, access roads, helipads and construction workshops, to the pre-existing topography and drainage contours;
  16. Reinstate off-site aggregate extraction facilities including borrow pits and quarries (opened specifically for construction or extensively used for construction);
  17. Implement repair and maintenance programs for reinstated sites;
  18. Consider the implementation of low impact seismic techniques (e.g. minimize seismic line widths (typically no wider than 5 m), limit the line of sight along new cut lines in forested areas (approximately 350 m));
  19. Consider shot-hole methods in place of vibroseis where preservation of vegetation cover is required and when access is limited. In areas of low cover (e.g. deserts, or tundra with snow cover in place), vibroseis machinery should be selected, but soft soil locations should be carefully assessed to prevent excessive compaction;
  20. Install temporary and permanent erosion and sediment control measures, slope stabilization measures, and subsidence control and minimization measures at all facilities, as necessary;
  21. Regularly maintain vegetation growth along access roads and at permanent above ground facilities, and avoid introduction of invasive plant species. In controlling vegetation use biological, mechanical and thermal vegetation control measures and avoid the use of chemical herbicides as much as possible. If it is demonstrated that the use of herbicides is required to control vegetation growth along access roads or at facilities, then personnel must be trained in their use. Herbicides that should be avoided include those listed under the World Health Organization recommended Classification of Pesticides by Hazard Classes 1a and 1b, the World Health Organization recommended Classification of Pesticides by Hazard Class II.
You are here: HomeThreatsOnshoreOnshore Environmental Risks - Terrestrial impacts and project footprint
  • ASMAA - Algarve Surf and Marine Activities Association
    NIPC: 510 381 952
    Tel: 00 351 282 182 103
    This email address is being protected from spambots. You need JavaScript enabled to view it.
    asmaa-algarve.org
    Rua Dr. Alberto Iria
    Lote 12, R/C Esq
    Porto de Môs
    Lagos 8600-580
    Portugal
Go to top